December 18, 1996, Constructor May 1997

Eichleay Update

Arnold & Porter Article
The Eichleay formula was first adopted in 1960 by the Armed Services Board of Contract Appeals as a means of calculating a contractor's unabsorbed home office overhead costs. The Federal Circuit has reaffirmed the Eichleay formula, holding that it is the only proper method for calculating unabsorbed home office overhead costs. The Defense Contract Audit Agency (DCAA), however, has issued revisions to its audit manual seemingly at odds with this holding.
 
Construction contractors use the Eichleay formula to account for unabsorbed overhead caused by a government delay or suspension of work. Overhead includes both the costs of running the home office and field office at the job site. The Eichleay formula involves three steps. First, the delayed contract billings are divided by the contractor's total billings and multiplied by total home office overhead to arrive at the allocable home office overhead. Second, this allocable home office overhead figure is divided by the days required to perform the delayed contract to determine the daily overhead rate. Finally, the daily overhead rate is multiplied by the number of days delay to produce the total overhead damages.
 
To take advantage of the Eichleay formula, a contractor must prove that: 1) the government caused the delay of work; 2) the delay involved a complete or partial suspension of work; and 3) the contractor was unable to take on other work during the delay period. The actual cause of the delay is not important, as long as the government was at fault. The key to recovery is the interruption of a contractor's stream of income. Thus, change orders in a contract generally will not result in Eichleay damages, but a delay where a contractor must "standby" will. Basically, the contractor must show that, as a result of a government delay, it was performing substantially less work than anticipated.
 
The DCAA audit manual raises important issues because it contradicts the Federal Circuit's pronouncement that the Eichleay formula is the only proper method of calculating unabsorbed overhead costs. The audit manual authorizes government auditors to adjust the Eichleay formula, or use an alternative formula, if inequitable results would occur. The manual, however, does not define what alternative method may be used or what "inequitable results" means.
 
The Federal Circuit has attempted to clarify the circumstances under which the Eichleay formula will apply, although the Satellite case adds confusion in this area. Nonetheless, the DCAA audit manual conflicts with the court's recent rulings. While the DCAA's position is not be binding on courts, it may make negotiations with the government more difficult.